针对1×7普通钢绞线锚索用于高应力动压巷道支护时破断力小、延伸率低、预应力小,控制围岩变形效果差的问题,根据高应力动压巷道围岩变形特点及支护系统要求,提出了1×19矿用钢绞线高强锚索支护技术。通过对高强锚索支护材料的试验分析,测定了新型1×19矿用钢绞线的拉断载荷及其延伸率,确定了其配套锚具、托板及锚固剂,并结合试验巷道81202回风巷的采矿地质条件,设计了1×19矿用钢绞线高强锚索支护方案。最后,现场工业性试验表明:相对于1×7普通钢绞线锚索支护,1×19矿用钢绞线高强锚索支护有效控制了巷道围岩变形,围岩变形量减小了约30%左右,巷道断面收缩率控制在5%以内,保证了巷道的正常使用。
Aiming at the problem of 1 × 7 common strand anchor used in high stress dynamic pressure roadway support with small breaking force, low elongation, small prestress and poor control effect on surrounding rock deformation, according to the deformation of surrounding rock of high stress dynamic pressure roadway, Characteristics and support system requirements, proposed 1 × 19 mine strand steel wire rope supporting technology. The tensile load and elongation of the new type 1 × 19 mining steel strand were determined through the test and analysis of the high strength anchor cable support material. The anchorage, pallet and anchoring agent were confirmed. Combined with the test lane 81202 Return airway mining geological conditions, the design of 1 × 19 mine strands of high-strength anchor cable support program. Finally, field test shows that relative to 1 × 7 common strand anchor support, 1 × 19 mine strand steel high-strength anchor cable support effectively control the deformation of surrounding rock, reducing the deformation of surrounding rock About 30%, the tunnel section shrinkage control within 5%, to ensure the normal use of roadway.