我厂铸造车间四立柱气动微震造型线,由于浇注位置比出铁位置高400毫米,在安装浇注轨道时采用了汽吊提升装置(如图所示)。升降轨道的两端分别装了上升行程开关和下降行程开关:当升降浇注包滚轮经过升降轨道低端,触动上升行程开关,通过二位四通双电控滑阀使汽吊动作,将升降轨道拉至与上轨道水平位置;当升降包进入上轨道,又触动下降行程开关,汽吊又一次动作、轨道下降复位。这样解决了高度差的问题,效果较好。
Our factory foundry four-column pneumatic microseismic modeling line, due to casting position 400mm higher than the iron position, the installation of pouring track using steam lifting device (as shown). The lifting track is equipped with an up-stroke switch and a down-stroke switch respectively at both ends of the lifting track. When the lifting-in-package bag roller passes through the lower end of the lifting track and touches up the up-stroke switch, the gas-lift is moved through the two- Pull to the horizontal position with the track; when the lift package into the track, but also touch the descent switch, the crane again action, the track down reset. This solved the problem of height difference, the effect is better.