对ACP1000三代核电厂核辅助厂房通风系统的设计进行了介绍。指出在方案设计时要做到系统功能明晰、系统设置合理;在系统布置时要做到机房紧凑,并适当通过通风竖井和就地空调设备的使用减少风管的布置;应根据系统功能选用合适的设备,并通过合理的控制保证系统的正常运行。
The design of ventilation system of nuclear auxiliary workshop in ACP1000 third generation nuclear power plant is introduced. It is pointed out that the function of the system should be clear and the system should be set reasonably in the design of the system. When the system is arranged, the engine room should be compact and the layout of the air duct should be reduced properly through the use of ventilation shafts and local air conditioning equipment. Equipment, and through the reasonable control to ensure the normal operation of the system.