在目前我国实行工程量清单的计价模式下,工程项目实行着固定总价合同或固定单价合同。本文根据我国这几年的工程量清单实施情况和工作积累,以及参照国外的发展经验,提出了工程造价动态管理调整的方法:实际价格调整法、调整文件计算法、工程造价指数法,并根据项目的不同特点,本文分别说明了各种方法的适用范围及优缺点等。
At present, China’s implementation of the bill of quantities mode of valuation, the project implementation of a fixed total price contract or a fixed unit price contract. This article based on the implementation of the bill of quantities in our country in recent years and accumulation of work, as well as with reference to foreign experience in development, proposed a dynamic management of project cost adjustment method: the actual price adjustment method, the adjustment file calculation method, construction cost index method, The different characteristics of the project, this article shows the scope of application of various methods and advantages and disadvantages.