一、前言 1980年前后,石油价格的高涨导致重新对水电设备作出评价并先后建造了许多大型水电站。富士公司从承制加拿大雷韦尔斯托克斯发电站的495MW×4台混流式水轮机为起点也制造了许多创纪录产品。但随后每年机组总容量和单机容量都增长缓慢,机组亦
I. Preface The ups and downs in oil prices around 1980 led to a reassessment of hydropower equipment and the construction of many large hydropower plants. Fuji has also produced a number of record-breaking products starting with 495MW × 4 Francis turbines that make up Revelstoke Power Station in Canada. However, the total unit capacity and stand-alone capacity will increase slowly each year