1997年4月10日,四川省科委、四川省机械工业厅在德阳主持召开了我公司为云南漫湾水电站研制的5台250MW 水轮发电机组科技成果鉴定会。漫湾水电站是国家“七五”计划的重点水电项目之一,也是我国西南地区第一座百万千万级电站。该电站机组是国内水电设备首次采用招标投标方式确定由我公司承制的。其5台250MW 水轮发电机组已分别于1993年6月至1995年6月顺利投产,至1997年3月,累计发电157亿 kW·h。在听取研制单位介绍了机组的设计、制造、测试情况,观看了电站运行情况录像、审
On April 10, 1997, Sichuan Science and Technology Commission and Machinery Industry Office of Sichuan Province hosted the scientific and technological appraisal meeting for 5 sets of 250MW hydro-generating sets developed by our company for Mannan Hydropower Station in Deyang. Manwan Hydropower Station is one of the key hydropower projects under the national “75” plan and the first one-million-millionth power station in Southwest China. The power station unit is the first domestic hydropower equipment used to determine the bidding by the company’s system. Its 5 250MW hydro-generating units have been successfully put into operation from June 1993 to June 1995, respectively, and by March 1997, they have generated a total of 15.7 billion kW · h of electricity. In listening to the development unit introduced the unit design, manufacture, test situation, watched the operation of the power station video, trial