我矿产量逐年提高,职工人数不断增加,生活用水很紧张,迫切需要建一座水塔,而附近生产队所能提供的土地,正在采空区上部,本文试图从我矿历年来积累起来的地面建筑与采掘关系的实测资料进行分析,并对兄弟矿山行之有效的计算公式和技术措施进行研究,找出解决水平和缓倾斜矿体地面建筑与采掘合理性问题的方法,从理论上说明在该采空区上部建造高达28米多、容量为100吨水塔的可能性。一、概况1.我矿从1949年到1959年,还是延用采高为:0.7~1.05米的矮工作面开采、全充填管
As mine production increases year by year, the number of workers and staff members is on the rise, and domestic water consumption is very tight. There is an urgent need to build a water tower. The land that the nearby production team can provide is in the upper part of the goaf. And mining relationship between the measured data analysis, and effective mining brothers formula and technical measures to study to find out the level and gently inclined ore body surface construction and mining rationality of the problem, from the theory that the mining Empty area up to build up to 28 meters, the capacity of 100 tons of water tower possibilities. First, an overview 1. I mine from 1949 to 1959, or continue to use mining height: 0.7 ~ 1.05 meters of the short face mining, fully filled tube