高墩、超小曲线半径(R=180m)、高墩40m箱梁架设,用普通架桥机按照正常的施工方法,存在架桥机过孔和喂梁两方面的困难,采用吊车架梁法,受墩高和场地限制;搭设满堂支架架梁、加宽盖梁架桥机架设法,用时长,费用高;双爬杆钓鱼架梁法,安全性很难保证等诸多困难,通过技术攻关,采用增加临时支腿以及旋转、横移架桥机的办法,顺利完成过孔和喂梁的技术难题,安全、保质、快速的完成了箱梁架设。
High pier, ultra-small curve radius (R = 180m), high pier 40m box girder erection, with the usual erection machine in accordance with the normal construction methods, there are bridging machine cross-hole and feed the beam two difficulties, the use of crane beam Law, by the pier height and site constraints; erecting full support beam, widening girder bridge frame to try, with the long time-consuming, high cost; double-pole fishing beam method, security is difficult to guarantee and many other difficulties through technology To tackle this problem, we adopted the method of adding temporary outriggers, rotating and traversing the erecting machine to smoothly complete the technical problems of the through holes and the feeding beams, and completed the erection of the box girders in a safe, quality and speedy manner.