南京水建在泰州引江河二期工程的施工过程中采用传统施工方式,通过释放浮标、插竹竿及水尺等方式进行施工引导,这种传统方式无法保证施工精度及施工工期。而徕卡测量系统挖掘引导系统3D版很好地解决了这个问题。施工数据的导入实现了施工位置的精确引导,在施工过程中还可以记录施工位置、挖掘深度、坡度等信息,提前了施工进度,减少了重复作业,避免了漏挖现象,提高了施工精度及效率。
Nanjing Water Construction adopted the traditional construction method during the construction of the second stage of the Yangtze River diversion project in Taizhou and guided the construction by releasing buoys, inserting bamboo poles and water meters, which could not guarantee the construction accuracy and construction period. The Leica Geosystems 3D guidance system solved this problem very well. The introduction of construction data can guide the construction site accurately. During the construction process, information such as construction site, excavation depth and slope can be recorded. Construction progress is advanced, repetitive work is reduced, leakage phenomenon is avoided, construction accuracy is improved, effectiveness.