论文部分内容阅读
自2013年以来,我国的光伏电站建设规模日渐扩大,但光伏电站质量问题频频爆发,行业产品质量以及使用年限问题日渐成为整个产业亟须解决的问题。三成光伏电站不合格“光伏电站组件的质量问题由来已久,深层次的原因与投资方在利益驱使下的运用补贴政策来”跑项目、骗补贴、以次充好“等做法是分不开的。”某大陆硅片商内部人士说。据光伏行业协会公布的数字,目前建成的电站里大概三
Since 2013, the construction scale of PV power plants in our country has been expanding day by day. However, the quality problems of PV power plants have been frequent and the product quality and service life of the industry have gradually become the problems that the entire industry needs to solve urgently. 30% failed to PV power station “The quality of PV power plant components has a long history, the deep reason and investors use the subsidy policy driven by profit to” run the project, cheat subsidies, shoddy “approach is Can not be separated. ”Some mainland silicon chip insiders said. According to figures released by the PV Industry Association, there are about three power plants currently built