西曲矿井是全国重点建设项目古交矿区的第一个投产井,设计能力为年产300万吨。1979年8月1日开工,1984年12月1日投产,建设工程为5年4个月,先期投产的工作面长度达57%,井巷工程质量优良品率占60.85%。国家验收委员会对该矿井的验收鉴定评语是“施工速度快、建设周期短、工程质量好,验收总评为优良”。
Xiqu Mine is the first production well in Gujiao Mining Area, a national key construction project, with an annual design capacity of 3 million tons. August 1, 1979 started production December 1, 1984 put into operation, construction of 5 years and 4 months, the first production of the working face up to 57% of the length of the length of the well project quality products accounted for 60.85%. National Acceptance Committee of the mine acceptance assessment review is “fast construction speed, short construction period, good project quality, acceptance of the total rating of excellent.”