1982年SELI公司中标承包修建在意大利弗利附近的Acquedotto della Romagna工程的7.2km长的S·索菲娅压力隧洞。卡罗·格兰多里(CarloGrandori)博士给出罗宾斯公司的直径为3.5m的118-221型硬岩双护盾隧道掘进机的详细技术规范。该掘进配上SELI公司设计的后配套系统一起穿过了6.2km的复理层地层构造,此构造包括一个延伸1500多米的较大范围的断层带。月平均进尺为520m,其中有8周时间为固结40m宽的粘土填充的断层而中途停工。
In 1982, SELI won the bid to build the 7.2 km S Sofia pressure tunnel in the Acquedotto della Romagna project near Forli, Italy. Dr. Carlo Grandori gives a detailed technical specification for Robbins’ 3.5-m diameter Type 118-221 hard-rock double-shield tunnel boring machine. The excavation, along with the SELI-designed back-up system, traverses a 6.2km flysch formation that includes a large range of fault zones that extend over 1,500 meters. The average monthly footage was 520m, with eight weeks stopping work on a clay-filled fault that consolidated 40m wide.