截止目前,燕山水库枢纽工程基本完成年度目标建设任务。据统计数据显示,工程主要形象进度为泄洪洞工程:全部完成;大坝工程:土石方开挖全部完成,坝体填筑达到设计高程,上下游护坡工程完成85%;溢洪道工程:土石方开挖全部完成;交通桥119m高程以下混凝土全部完成;尾水渠及王文成沟浆砌石全部完成;闸室上部结构完成60%,闸门
Up to now, Yanshan Reservoir Project basically completed the annual target construction tasks. According to the statistics, the main progress of the project is the spillway tunnel project: all completed; dam project: the earthwork excavation is completed, the dam body filling reaches the design elevation, and the upstream and downstream slope protection works are completed by 85%; spillway works: all of the earthwork excavation Completed; traffic bridge 119m elevation below the concrete all completed; tailings and Wang Wencheng ditch masonry all completed; the upper part of the chamber to complete 60% of the gate