论文部分内容阅读
瑞典波立顿阿克提波拉克乌登矿,是一座全部采用无轨系统,年产32万吨的地下矿山。生产采用水平分层充填法回采及水力充填。该矿特别令人感兴趣是采矿生产凿岩中使用了电力液压凿岩台车(阿特拉斯,克普克 H132—2臂台车)。这种液压凿岩机,风动机械凿岩效果显著。乌登(Udden)矿床位于瑞典互斯特波登(Vasterbotten)省诺旧市(Novsjo)斯科莱夫特(Skellef-tea)河的南面约1.5公里,开特查斯卡(Kedtrask)矿床的西南约2.5公里。矿石用卡车经30公里公路运往波立顿(Boliden)处理。
Acre Pollak Udon mine in Bolton, Sweden, is an underground mine with an annual production capacity of 320,000 tons, which is entirely trackless. The production of horizontal stratified filling method of mining and hydraulic filling. This mine is of particular interest is the use of electric hydraulic rock drilling rigs (Atlas, Kopf H132-2 arm trolley) in mining production. This hydraulic rock drill, pneumatic drilling significant effect. The Udden deposit is located about 1.5 km south of the Skellef-tea river in Novsjo, the capital of Sweden’s Vasterbotten province. The Udden deposit is located in the Kedtrask deposit About 2.5 km southwest. The ore is transported by truck to Boliden over a 30 km highway.