2012年10月1日,中材国际天津公司摩洛哥FES项目顺利实现大窑点火。FES项目属于EP+电气安装与调试项目。在公司领导的正确指导及公司各部门的大力支持下,项目部全体员工先后克服了项目拖期、多家当地安装公司参与、施工场地狭小、当地酷热气候、大风扬尘天气等多种困难,团结奋斗,努力进取,积极与业主和当地安装公司配合,历经半年多的调试,终于顺利实现项目一次性点火成功!经过各方共同努力,项目继10月1日晚上点火后,于
On October 1, 2012, the FES project of Sinoma International Tianjin Company realized the kiln ignition successfully. FES project belongs to the EP + electrical installation and commissioning project. With the correct guidance of the company leaders and the strong support of all departments of the company, the project team all over the project have overcame many difficulties such as project tardiness, participation of many local installation companies, small construction sites, hot local climates and windy dusty weather, Struggling, Endeavoring, Actively Cooperating with Owners and Local Installation Companies, After More than Six Months of Commissioning, Successfully Realizing the One-time Ignition Success of the Project! Through the concerted efforts of all parties, following the project’s ignition on the evening of October 1,