1.总则1.1根据国家计委基本建设项目审批程序,凡列入长期计划或建设前期计划的项目,应有批准的项目建议书。报送项目建议书,应随文附送已经主管部门批准的预可行性研究报告文件。为统一水电工程项目预可行性研究报告编制的原则、工作内容和深度要求,特制定本暂行规定(试行)。1.2本规定适用于编制新建、扩建的大中型水电预可行性研究报告。对装机容量10万kw以
1. General 1.1 According to the approval process of the State Development Planning Commission’s basic construction project, any projects listed in the long-term plan or the pre-construction plan shall have the approved project proposals. Submission of project proposals should be attached with the text of the pre-feasibility study report has been approved by the competent authority. In order to unify the principles, contents and depth requirements for compiling the pre-feasibility study report of the hydropower project, this Provisional Regulation (Provisional) is formulated. 1.2 The provisions apply to the preparation of new and expanded pre-feasibility study report of large and medium hydropower. Installed capacity of 100,000 kw