一、对两年多来论证工作的回顾和评价自从中央和国务院在1986年6月下达15号文件,责成我们负责重新组织三峡工程的论证工作以来,已经两年零八个月了。我们根据中央和国务院的要求:“在广泛征求意见、深入研究论证的基础上,重新提出可行性研究报告。”成立了14个专家组负责进行专题论证。聘请了21位特邀顾问,以接受各界的指导。最后由长办根据专家组的论证成果重新综合编写了可行性研究报告,提交本次大会审议。论证工作进度比原计划延长了一些时间。这是因为我们坚握进度必须服从质量的原则,力求提出一个有科
I. Review and Evaluation of the Argumentation over Two Years Since the central government and the State Council issued Document No.15 in June 1986, urging us to take charge of reorganizing the feasibility of demonstrating the Three Gorges Project, it has been two years and eight months. In accordance with the requirements of the Central Government and the State Council: “We re-proposed the feasibility study on the basis of extensive solicitation of opinions and in-depth research and feasibility studies.” We set up 14 expert groups to conduct thematic demonstrations. Hired 21 invited consultants to accept the guidance of all walks of life. Finally by the Office of long-term experts based on the demonstration results of the re-synthesis of the feasibility study prepared by the General Assembly for consideration. Demonstrate the progress of work than the original plan to extend some time. This is because we must strictly abide by the principle of quality and make every effort to propose a course