主要介绍了在繁华的市区进行盾构法施工过程中,在地下管线较多,周边环境复杂的条件下,进行盾构刀具检查、更换或修复刀盘、刀座而设置的地面加固点施工的新思路、新方法。通过在隧道旁侧开挖小竖井,然后在地下管线下部开挖横通道,最后在隧道正线上方施做洞桩的施工方法,解决隧道正线上方地下管线较多而无法直接进行地面加固的难题。
Mainly introduced in the bustling urban construction of the shield method, under the conditions of more underground pipelines, the surrounding environment is complex, the shield cutter inspection, replacement or repair of the cutter plate, knife set and the ground reinforcement points construction New ideas, new methods. By excavating small vertical shafts on the side of the tunnel, then digging horizontal passages in the lower part of the underground pipeline, and finally applying the construction method of the hole piles above the main line of the tunnel to solve the problem that there are many underground pipelines above the mainline of the tunnel and can not be reinforced directly problem.