第二铜矿八月份的探矿计划中,确定117号坑道为探索90M80号坑道下部矿体的重点探矿。这个重点探矿虽然得到行政干部、技术人员及工人们的重视,但是由于月初未能很好的进行组织工作,因此进度与效率都比较差。经上级一再指示必须专人负责,加强坑道小组的组织及贯澈直进式凿岩法,始由八月十三日以後号召全组向完成70M目标奋闘。兹将完成情况及工作经验总结如下: 一、任务完成情况
In the prospecting program of the second copper mine in August, No. 117 tunnel was identified as the key exploration for exploring the lower part of No. 90M80 tunnel. Although the focus of this prospecting has received the attention of administrative cadres, technicians and workers, the progress and efficiency are relatively poor due to the failure to organize well at the beginning of the month. After repeatedly instructing the supervisor to be in charge of the work, strengthening the organization of the tunneling team and the direct drilling method, the whole group was urged to complete the 70M goal by August 13. It will be completed and work experience is summarized as follows: First, the task to complete the situation