论文部分内容阅读
BIM(建筑信息模型)技术的发展使建筑领域产生了第二次变革,但BIM技术在地下输电工程的结构设计中应用较少。基于国家电网项目中即墨站220 k V地下输电工程,以输电网中的工作井为研究对象,在BIM建模软件Revit中建立了工作井模型族库,实现参数化建立工作井的BIM模型,并将模型导入结构分析软件Robot中进行计算分析。该项目实现了工作井设计及计算的批量化操作,提高了设计人员的工作效率。
BIM (Building Information Modeling) technology has led to a second revolution in the field of construction, but BIM technology is less used in structural design of underground power transmission projects. Based on the 220 kV underground power transmission project at Jimo Station in the State Grid project, the working wells in transmission network are taken as research objects. A working well model library is set up in BIM modeling software Revit to realize parameterized establishment of a well BIM model. The model is imported into structural analysis software Robot for calculation and analysis. The project has realized the batch operation of well design and calculation, and improved the work efficiency of designers.