1999年7月 12日下午,重30吨,高2.45米,外径15.5米的小浪底水利枢纽水力发电厂6号机组的发电机定子一次吊装就位,比计划提前4天。施工现场的中外专家无不欢欣鼓舞。我们采取高角度即俯角拍摄,记录了这一激动人心的场面。(图一) 小浪底水利枢纽水力发
On the afternoon of July 12, 1999, the generator stator of No.6 unit of Xiaolangdi Hydro Project, weighing 30 tons, 2.45 meters high and 15.5 meters in outer diameter, was hoisted in a hoist four days earlier than planned. Chinese and foreign experts at the construction site all rejoiced. We took a high angle that depression shot, recorded this exciting scene. (Figure 1) Xiaolangdi Multipurpose Hydropower Project