本文主要对斜拉链吊装专项施工方案进行论述,工程基本数据为钢结构桁架(GHJ1),总长度58.248m,与水平面成38°夹角,总重量约76t。钢桁架下端与烧成窑头熟料输送地沟出口相连,与支承面采用销轴连接,底标高2.000m。顶端与熟料输送及储存中心42.500m平面钢平台相连,支承面为滚动支座。中部设钢支架(GZJ1),支承于熟料输送及储存库壁上,GZJ1上端与钢桁架及下端与库壁支端面均采用销轴连接。GHJ1因跨度大,重量大,其吊装过程作为本方案编制过程控制的重点。
This article mainly discusses the special construction scheme of inclined zipper hoisting. The basic data of the project is the steel truss (GHJ1) with a total length of 58.248m and an angle of 38 ° with the horizontal plane, with a total weight of about 76t. The lower end of the steel truss is connected with the outlet of the kiln clinker conveying ditches, and the bearing surface is connected with a pin, the elevation of the bottom is 2.000m. The top is connected with the 42.500m flat steel platform of the clinker conveying and storage center, and the supporting surface is a rolling bearing. Central steel support (GZJ1), supported by the clinker transport and storage on the wall, GZJ1 and the upper end of the steel truss and the lower end of the wall with the wall support pin ends are connected. GHJ1 due to large span, heavy weight, the lifting process as the focus of the preparation process control.