2000年12月29日,由上海市水务局为主承担的“黄浦江河口建闸工程规划研究”课题通过上海市科委主持的专家鉴定。该报告依据水情工情变化和黄浦江沿岸高潮位趋势性抬高的事实,对上海市防洪标准及设计水位进行了分析。在课题研究阶段防洪标准暂按千年一遇潮位考虑的前提下,报告研究比较了继续加高加固防汛墙和黄浦江河口建闸两个基本方案,认为:河口建闸是上海防汛安全的根本保障,此外在综合效益、运行管理及环境等方面也有优势。结合上海的实际情况,参照国外
December 29, 2000, led by the Shanghai Municipal Water Bureau “Huangpu River estuary gate construction planning research ” subject through the Shanghai Municipal Science and Technology Commission presided over the identification of experts. The report analyzes flood control standards and designed water levels in Shanghai based on the fact that hydrological conditions are changing and the trend of high tide levels along the Huangpu River rises. Under the precondition that the flood control standards are tentatively applied to the tide of the millennium, the report compares and studies two basic schemes of increasing the height of the flood control wall and the gate of the Huangpu River estuary, and concludes that the construction of the river mouth is the fundamental guarantee of the flood control safety in Shanghai In addition, there are advantages in terms of comprehensive benefits, operation management and environment. Combined with the actual situation in Shanghai, with reference to foreign countries