美国SRAM 2近程攻击导弹研制计划于80年代初开始执行,于1987年4月进入为期5年的全面研制阶段,导弹的主承包商为波音公司。SRAM 2预定在1990年进行第一次飞行试验,届时将进行约25次发射试验和联合研制/初始作战评估,并于同年9月进行首次实弹试射,1991年年中开始生产,1993年装备部队。到1997年计划生产1633枚。估计总费用(包括研制、试验、生产费用)为24亿美元(1986年币值)。
The development of the U.S. SRAM 2 short-range attack missile started in the early 1980s and entered full-scale five-year development in April 1987 with the main contractor for the missile being Boeing. SRAM 2 is scheduled to conduct its first flight test in 1990, when about 25 launch tests and joint development / initial operational evaluations will be conducted and the first live-fire test will be conducted in September of the same year. Production will begin in mid-1991 and in 1993 force. By the year 1997, it plans to produce 1633 pieces. The estimated total cost (including development, testing, production costs) was 2.4 billion U.S. dollars (1986 currency).