平顶山帘子布厂是从日本引进全套设备的工厂,年产锦纶帘子布13,000吨,空调工程由日本旭化成株式会社设计,空调设备也由该公司配套提供,这里仅就引进空调设备的情况作一个粗略的介绍。1)全装配带洗涤室金属空调箱(air-washer)共7台,纺丝冷风和卷绕冷风各一台,织布间一台,捻线车间四台,其中捻线车间的4台风量最大,每台风量为2634千米~3/小时,外形尺寸为宽6米,高4.4米,长4.6米。空调箱壳体为1.2毫米的镀锌钢板,
Pingdingshan Tienzi Fabric Factory is a factory that imports a full set of equipment from Japan. It annually produces 13,000 tons of nylon cord fabrics. The air conditioning project is designed by Asahi Kasei Corporation and air-conditioning equipment is also provided by the company. This is only a rough outline of the introduction of air-conditioning equipment. The introduction. 1) A total of 7 air-washers with washing rooms are installed, one for spinning cold wind and one for cold wind, one for weaving, four for twisting line workshops, and four air flow rates for the stencil workshop The largest, each air flow rate is 2634 km~3/hour. The external dimensions are 6 meters wide, 4.4 meters high and 4.6 meters long. The housing of the air-conditioning box is 1.2 mm galvanized steel.