三峡杨家湾港散杂货码头是三峡工程的重要配套交通工程项目。该工程于1994年7月10日开工,合同工期120天,因设计变更等原因使工期顺延62天,计算竣工时间1995年1月7日,实际竣工时间1994年12月22日,较合同工期提前16天。长委三峡右岸工程监理总站(1995年改为长委三峡工程监理部)坚持以“科学态度,严谨作风,求实精神,服务观念”为宗旨,以工程建设承包合同为依据,运用业主单位授于的权限,与参加工程建设各方密切协作,指导、检查、监督承包商单位严格履行工程建设承包合同,通过监理工程师有序、高效的工作和技术技能运用,满足了三峡工程正式开工所需水泥集装箱运输的需要。
Three Gorges Yang Bay Bay bulk groceries terminal is the Three Gorges Project an important supporting traffic engineering projects. The project started on July 10, 1994, the contract period of 120 days, due to design changes and other reasons to make the project delay of 62 days, the completion of the calculation of January 7, 1995, the actual completion time December 22, 1994, compared with the contract duration 16 days in advance. The Standing Committee of the Three Gorges Right Bank Engineering Supervision Station (renamed the Three Gorges Project Supervision Department in 1995) adhered to the principle of “scientific attitude, rigorous style, realistic spirit and service concept”, based on the project construction contract, And closely cooperate with all parties involved in the project construction to instruct, inspect and supervise the contractor’s units to strictly perform the contract of construction contract. Through the orderly and efficient supervision of engineers and the application of technical skills, the cement needed for the official start of the Three Gorges Project Need for container transport.