我矿自营建设的竖井,深358米,净直径5.2米,荒直径6.05米,永久支护采用浇灌混凝土,标号为150号,浇灌厚度350毫米。井颈段采用井圈背板作临时支护;基岩中利用金属滑模浇灌,不作临时支护。当掘至马头门上部时,因施工方案要求在马头门上部9.7米段井筒内作临时支护,经过仔细研究,最后确定采用废钢丝绳锚杆作该段井筒的临时支护,实用证明效果良好。
I mine self-building shaft, 358 meters deep, the net diameter of 5.2 meters, 6.05 meters diameter waste, with permanent irrigation using pouring concrete, No. 150, watering thickness of 350 mm. Wellbore section using well back for temporary support; bedrock using metal sliding mode irrigation, not for temporary support. When digging to the top of Ma Tau Mun, due to the construction scheme, it is required to make temporary support within the 9.7 m section of wellhead in the upper part of Ma Taumen. After careful study, it is finally proved that the use of scrap steel wire rope anchor as temporary support for the wellbore is practical proof Good effect.