结合铜矿现状,按四维破磨理论设计2.7×3.7m双仓碎磨机,转速超费氏临界转速5%,实际混合充填率56%左右,进料仓装超大钢球。用它替代中细碎和球磨的生产流程设备,生产能力40 t/h左右,完全能满足某矿生产规模≤25万t/a的需求。预计碎磨用电单耗将由目前18kW h/t下降到8kW h/t以下,全年节电200万kW h以上,并大幅度降低设备维修费用和提高劳动生产率。实施改造,能为企业创造较好的经济效益。
Combined with the current situation of copper mine, according to the four-dimensional crushing theory, the 2.7 × 3.7m double chamber crusher is designed. The critical speed of the superfine rotor speed is 5%. The actual mixed filling rate is about 56%. Use it to replace the crushing and ball mill production process equipment, production capacity of 40 t / h or so, fully able to meet the scale of a mine production ≤ 250,000 t / a demand. It is estimated that the unit consumption of grinding and grinding will be reduced from the current 18kW h / t to below 8kW h / t, saving more than 2 million kWh in the whole year and greatly reducing the equipment maintenance cost and improving the labor productivity. Implementation of transformation, for enterprises to create better economic efficiency.