1 基本情况 我院从2000年2月22日成立医院“一号工程”建设领导小组、确立具体实施方案开始,3月份门诊系统开始使用,5月1日护士站正式启用,6月1日医生站正式启用,到7月1日全院网络开通并全面正式运行。短短4个月间,我们经过了硬件设备选定型及招标投标、网络布线、站点确定、网络中心建设、设备安装和调试,以及软件初始化、工作站版本选择、软件测试、模块测试、模拟运行、分期上网和人
1 Basic situation Our hospital from February 22, 2000 set up a hospital “one project” leading group to establish the specific implementation plan began in March outpatient system began to use, May 1 nurse station was officially opened on June 1, the doctor Station officially opened until July 1 the hospital network opened and fully operational. In just 4 months, we passed the selection of hardware equipment and bidding, network cabling, site identification, network center construction, equipment installation and commissioning, and software initialization, workstation version selection, software testing, module testing, simulation run , Staging online and people