论文部分内容阅读
一、概况位于安徽省利辛县阚町镇北的阚町泵站,是茨淮新河上两个梯级泵站的二级站,是阚町枢纽工程的主要组成部分。泵站原规划以发展灌溉为主,兼顾排涝、保航,按灌溉规划确定装机规模。站内设2.8CJ-70立式全调节大型轴流泵(铭牌标称:D=2.8米、n=150rpm、H=5.6米、Q=21立方米每秒),配TDL-325/36-40型1600KW三相同步电动机四台。1973年开工至1980年安装完毕,仅1981年5月进行72小时联合运转,至今尚未投入运行。由于种种原因,今后开机抽水的机遇也不多。为此,阚町闸管
I. Overview Kancheon Pump Station, located in the north of Kancheon Town, Lixin County, Anhui Province, is the second station of two cascade pumping stations on the New River of Zhuaigai, and is the main component of Kan-cho hub project. The original pumping station planning to develop irrigation, taking into account the drainage, security, according to the irrigation plan to determine the installed capacity. The station is equipped with 2.8CJ-70 vertical fully adjustable large axial flow pump (nameplate nominal: D = 2.8m, n = 150rpm, H = 5.6m, Q = 21m3) with TDL-325 / 36-40 1600KW three-phase synchronous motor four. Started in 1973 until installation in 1980, only in May 1981 for 72 hours of joint operation, has not yet put into operation. Due to various reasons, there are not many opportunities for pumping in the future. To this end, Kan town brake tube