梨温高速公路广丰连接线西溪中桥原设计上部构造为3-13米空心板梁桥、下部构造为双柱式钻孔灌注桩墩台,桩径1400mm。2003年7月桩基钻孔时,发生塌孔现象。经设计、监理等单位专家认定,初步推断该桥桥基地质情况较为复杂,可能遇上溶洞或溶洞群。2003年8月,经有关地质勘探部门勘探,确定该桥桥址处于溶洞群。为减少桩基工程量,降低工程造价,该桥上部构造由3—13米空心板梁变更为2—20米预应
Liwen Expressway Guangfeng connecting line Xixi Zhongqiao original design upper structure is 3-13 meters hollow girder bridge, the lower part is constructed of double-column bored pile pier, pile diameter 1400mm. In July 2003 when the pile foundation borehole, borehole collapse occurred. The design, supervision and other experts believe that the initial inference of the bridge site of the geological conditions are more complex and may encounter karst cave or cave group. In August 2003, after exploration by the relevant geological exploration department, it was confirmed that the bridge site was in a cave group. In order to reduce the amount of pile foundation and reduce the construction cost, the structure of the upper part of the bridge was changed from 3-13m hollow slab to 2-20m