我处在××大桥使用液压提升收坡式滑动钢模板,进行五个空心桥墩的拖工,历时五个月,平均提升速度每24小时为2.2米(高墩有横隔板)至6.1米(低墩),最高达8米/24小时。混凝土质量内实外平,无接缝,符合设计要求,千斤顶杆钢筋全部回收。初步计算可节省脚手、模板等木料约110立方米,劳动力7,800工天。与实心桥墩比较,节约圬工935立方米。改善了施工条件,减轻了劳动强度,同时保障了施工的安全。
I was on the XX Bridge using hydraulic lift sliding sliding steel formwork, five hollow pier pier, which lasted five months, the average lifting speed of 2.2 meters every 24 hours (high pier with diaphragm) to 6.1 meters (Low pier), up to 8 m / 24 hours. In fact, the quality of concrete flat, seamless, in line with design requirements, lifting all the lifting rod. The preliminary calculation can save about 110 cubic meters of wood, such as scaffolding and stencils, and a workforce of 7,800 working days. Compared with the solid piers, saving workers 935 cubic meters. Improve the construction conditions, reduce labor intensity, while ensuring the safety of construction.