滑模施工是施工现浇混凝土工程的一个有效方法.它具有机械化程度较高,施工速度快,建筑物的整体性好,因而在国内外得到广泛的应用.下面浅析滑模施工中的一种新工艺——随滑随粉技术.随滑随粉技术其特点是随着墙体滑模不断升高,利用外挑的三排吊脚手,将外墙粉刷由下而上地跟着进行施工,墙体滑模到顶,外粉刷也跟随粉到顶,这就从根本上改变了外粉刷必须利用外脚手从上到下施工的传统工艺.这种施工工艺的优点是外墙粉刷随同滑模一同完成,节约了大量的外脚手材料,降低了工程成本;施工速度快,施工安全、文明.
Slipform construction is an effective method for the construction of cast-in-place concrete works. It has a high degree of mechanization, construction speed, building a good overall, and therefore widely used at home and abroad. The following analysis of a A new process - with sliding powder technology. With sliding powder technology is characterized by the rising wall sliding mode, the use of external pick three rows of hanging feet, the outer wall painting from the bottom up to follow In the construction, the wall slides to the top, and the exterior painting also follows the powder to the top, which fundamentally changes the traditional process that the outer painting must be performed from the top to the bottom with the outer scaffolding. The advantage of this construction process is that the outer wall is painted along with the slide. The mold is completed together, saving a lot of external scaffolding materials, reducing the project cost; construction speed, construction safety, and civilization.