后浇带按作用可分为三种:用于解决高层主体与低层裙房的差异沉降者,称为后浇沉降带;用于解决钢筋混凝土收缩变形者,称为后浇收缩带;用于解决混凝土温度应力者,称为后浇温度带。后浇带一般可同时考虑几种作用,但终究是临时性的措施,待将该处混凝土补齐后,才能得到充分发挥,所以施工也有特点。
Post-pouring belt can be divided into three according to the role: for the settlement of the difference between high-rise main body and the lower podium settlement, known as post-pouring settlement belt; used to solve the shrinkage deformation of reinforced concrete, known as post-pouring shrink; for Solve the temperature stress of concrete, known as after pouring temperature zone. After pouring with the general can take into account several roles at the same time, but after all, is a temporary measure to be completed after the concrete fill in order to get the full play, so the construction has features.