论文部分内容阅读
陆东煤矿选煤厂为15万吨/年的简易选煤厂,有设计能力为200吨的精煤仓4座。跳汰机精煤产品(<13毫米细粒精煤)由斗子捞坑提出后即通过胶带输送机入仓。自1981年1月投入生产以来,突出的矛盾就是精煤脱水问题,常因脱水时间长,煤仓周转不开而影响生产。后增设二台固定脱水筛,仓内精煤脱水效率虽有所提高,但仍需3~4天才能装车出厂,精煤水分
Ludong Coal Preparation Plant is a 150,000 tons / year simple coal preparation plant, with a design capacity of 200 tons of four coal bunker. Jig clean coal products (<13 mm fine-grained coal) raised by bucket fishing pit after the conveyor belt through the warehouse. Since January 1981 put into production, the prominent contradiction is the problem of clean coal dehydration, often due to dehydration for a long time, not open turnover of coal storage and affect production. After the addition of two sets of fixed dehydration screen, although the warehouse dewatering efficiency has improved, but still need 3 ~ 4 days to loading the factory, clean coal moisture