《国家电网》:在中电联2013年一季度全国电力供需形势分析预测报告发布会上,中国电力联合会副秘书长欧阳昌裕提到云南和四川等西南水电的外送能力接近饱和,面临大规模弃水风险,您能否谈谈今年四川水电外送的情况?与往年有哪些不同?王抒祥:这两年是四川水电集中投产的年份。今年大小水电投产加在一起超过1400万千瓦,明年还要投产1200万千瓦,后年1000万千瓦。三年差不多要投产4000万千瓦。相比之下,2013年四川电网的外送
National Grid: CEC’s first quarter 2013 national power supply and demand situation analysis and forecast report conference, China Electric Power Association, Deputy Secretary-General Ouyang Changyu mentioned Yunnan and Sichuan and other Southwest Hydropower delivery capacity close to saturation, facing a large Scale of waste water risks, can you talk about this year’s Sichuan hydropower delivery situation? What are the differences with the previous years? Wang Shixiang: These two years is concentrated in Sichuan Hydropower Year. This year the size of hydropower put together more than 14 million kilowatts, but also put into operation next year 12 million kilowatts, the following year 10 million kilowatts. Almost 40 million kilowatts will be put into operation in three years. In contrast, the outgoing Sichuan grid in 2013