姚孟3、4号机组是从比利时引进的。根据合同和设计分工,比利时和中方各自负责设计的项目,其主要内容如下。 (1) 汽轮发电机基座及其下部的平台由比利时负责设计并提供施工图纸。基座为现浇钢筋混凝土结构,基座所用材料及施工等均由中方负责。 (2) 锅炉钢架、锅炉紧身罩、炉顶屋面结构均由比利时设计并供货,但锅炉基础由中方设计。 (3) 主厂房内工艺系统由比利时负责设
Yao Meng’s Units 3 and 4 were imported from Belgium. According to the contract and design division of labor, Belgium and China are each responsible for the design of the project. Its main contents are as follows. (1) The base of the turbine generator and the platform below it are responsible for designing and providing construction drawings. The base is a cast-in-place reinforced concrete structure, and the materials and construction used for the base are all the responsibility of the Chinese. (2) Boiler steel frame, boiler hood, and roof structure are all designed and supplied by Belgium, but the boiler foundation is designed by China. (3) The process system in the main building is set up by Belgium