论文部分内容阅读
青海公伯峡水电站是国家“十五”重点工程、“西电东送”的启动项目。该工程于2001年8月开工建设,2006年8月竣工,曾获得中国建筑工程鲁班奖、中国电力优质工程奖、中国电力科学技术二等奖等奖项。评选专家认为:该工程在大型钢筋混凝土面板堆石坝施工中首次采用了自行混凝土挤压
Qinghai Gongboxia Hydropower Station is a national “Tenth Five-Year” key project, “West to East,” the start-up project. The project started construction in August 2001 and completed in August 2006. It won awards such as the Luban Prize of China State Construction Engineering, China Power Quality Project and the Second Prize of China Electric Power Science and Technology. Selection experts believe that: The project for the first time in the construction of large-scale reinforced concrete faced rockfill dam with its own concrete extrusion