【摘 要】北海——南宁——百色成品油管道工程经过南宁地区长约7.2km香蕉林。江苏油建项目部经过精心组织,在全体员工的共同努力之下,按期完成香蕉林管道安装施工任务。通过压缩施工作业带,少占用香蕉林地10000平方米,少砍伐约2000棵香蕉树;在地貌恢复完成后,蕉农们及时补植香蕉苗,降低了蕉农的经济损失。
【关键词】香蕉林;管道安装;灌溉系统;施工作业带
Banana forest lots Pipeline construction measures
Zhao Wen-hai
(Jiangsu Petroleum Exploration Bureau Oilfield Construction Division Jiangdu Jiangsu 225261)
【Abstract】North Sea - Nanning - Nanning, Baise Pipeline Project through the banana forest area of about 7.2km. Jiangsu Oil Ministry has been carefully organized to build the project in the joint efforts of all staff, and fulfill the banana forest pipeline installation and construction tasks. Construction jobs by compression with less forest land 10,000 square meters occupied by banana, small banana trees cut down about 2000; in landscape restoration is complete, banana banana seedlings were replanted in time, reducing the banana farmers of the economic losses.
【Key words】Banana forest;Pipeline installation;Irrigation systems;Construction operations with
1. 引言
由江苏油建承建的北海——南宁——百色成品油管道工程四标段,设计压力9.5MPa,采用X60 457×8.7/10.3mm直缝焊管,3PE防腐,一般管线埋深管顶覆土1m,年输送能力350万吨。四标段线路起于南宁屯里油库,途径三区二县,终于隆安县武鸣河,管线全长71km。沿线有香蕉、木薯、甘蔗、柑橘等经济作物,管线经过桩号为NBZ237-NBZ248长约7.2km连片规模种植的香蕉林,其间夹杂有少量的木薯地和甘蔗地,管线穿过净香蕉林长度约为5km。
2. 香蕉林管道安装应引起重视的问题
在香蕉林中进行管道安装施工值得引起重视的问题是:
2.1 尽可能压缩施工作业带宽度,少占一寸土地,让蕉农们多收获一串香蕉。
2.2 保护并恢复好香蕉林的灌溉系统,维持香蕉的正常生长环境要求(见图1)。
图1 地上喷灌系统 2.3 在灌水的停息期内完成施工任务,保持香蕉林的灌溉周期节奏。
2.4 由于香蕉特殊的生长需要:当地蕉农采用一垅一垅的种植方式,种植前需对香蕉地进行深翻,采用二犁二耙的方式对香蕉林土地松动再施肥以满足香蕉种植需要,翻地深度一般为地表以下1米,故管道管顶覆土应在2.5m以上。
2.5 施工中,人员、机械、管道等尽可能不损坏香蕉树。 综合考虑各种因素,项目部特别制定了香蕉林管道安装施工方案。
3. 香蕉林管道安装施工方案要点
3.1 测量放线:对管道路由进行优化,尽量利用垅间路、边角、沟渠边空地,避开主水管线敷设管道,减少赔青费用,降低蕉农损失。
3.2 作业带清扫:正常作业带清扫按建设方规定的8m宽进行。我们在香蕉林按6m宽度进行清扫,尽量保证作业带横断面只砍除3株,局部特殊地段4株,不允许超4株香蕉树。
图2 管沟开挖3.3 拆除地面灌溉系统:先拆除软胶管,收集到作业带外香蕉林中,再手工切割PE主管线,拆除后放置在香蕉树垅间,不得损坏。
3.4 拆除地下水管线:在蕉农的配合下,人工开挖出地下水管线,按上面方法拆除,断口进行临时封堵,防止泥土、杂物进入堵塞水管线。
3.5 开挖管沟时,提前做好防坍方措施,必要时采用打钢管排桩以防塌方,然后按照要求进行管沟开挖(见图2)。
3.6 管线下沟、辅助工序完成后,及时进行回填,回填到地下供水管线标高。
3.7 地下供水管线恢复:按原位置对PE管热熔焊、连接。
3.8 继续地表土恢复。
3.9 地上供水管线恢复:对主水管线进行热熔焊、连接,恢复软胶管连接,完成施工任务。
4. 香蕉林管道安装施工管理措施
4.1 教育每一名员工,提高质量意识,增强农田和经济作物的保护意识。工农一家,既要圆满完成管道安装任务,又要使蕉农的损失降到最低。
4.2 对参加香蕉林管道安装施工机组的作业带占用宽度进行考核,少占的给予奖励,超占的扣罚。
4.3 提前购置准备好香蕉林水管线恢复材料、零部件及熔焊机等机具。 4.4 进行分段施工,服从香蕉林灌水周期节奏。 4.5 施工期间时值酷暑,香蕉林不透风,象蒸笼一样,蚊虫、毒蛇又多,要合理安排施工作业时间,防止中暑及蚊虫、毒蛇攻击,保证工人身体健康。 4.6 施工结束后听取蕉农意见,力求蕉农满意。 5. 结束语 经过项目部精心组织,在全体员工的共同努力之下,按期完成了香蕉林管道安装施工任务。经建设方、监理和质量监督部门检查,工程施工质量合格。通过压缩施工作业带宽度,少占用香蕉林地10000平方米(约15亩),按建设方要求,施工占地减少了25%,少砍伐约2000棵香蕉树。在项目部合理部署、科学安排下,加快施工节奏,在地貌恢复完成后,蕉农及时补植香蕉苗,降低了蕉农的损失。经过对沿线蕉农的回访,蕉农们对我单位在香蕉林地的管道安装所采取的少占香蕉林地、尽快恢复种植、降低蕉农损失的措施感到满意。
【摘 要】北海——南宁——百色成品油管道工程经过南宁地区长约7.2km香蕉林。江苏油建项目部经过精心组织,在全体员工的共同努力之下,按期完成香蕉林管道安装施工任务。通过压缩施工作业带,少占用香蕉林地10000平方米,少砍伐约2000棵香蕉树;在地貌恢复完成后,蕉农们及时补植香蕉苗,降低了蕉农的经济损失。
【关键词】香蕉林;管道安装;灌溉系统;施工作业带
Banana forest lots Pipeline construction measures
Zhao Wen-hai
(Jiangsu Petroleum Exploration Bureau Oilfield Construction Division Jiangdu Jiangsu 225261)
【Abstract】North Sea - Nanning - Nanning, Baise Pipeline Project through the banana forest area of about 7.2km. Jiangsu Oil Ministry has been carefully organized to build the project in the joint efforts of all staff, and fulfill the banana forest pipeline installation and construction tasks. Construction jobs by compression with less forest land 10,000 square meters occupied by banana, small banana trees cut down about 2000; in landscape restoration is complete, banana banana seedlings were replanted in time, reducing the banana farmers of the economic losses.
【Key words】Banana forest;Pipeline installation;Irrigation systems;Construction operations with
1. 引言
由江苏油建承建的北海——南宁——百色成品油管道工程四标段,设计压力9.5MPa,采用X60 457×8.7/10.3mm直缝焊管,3PE防腐,一般管线埋深管顶覆土1m,年输送能力350万吨。四标段线路起于南宁屯里油库,途径三区二县,终于隆安县武鸣河,管线全长71km。沿线有香蕉、木薯、甘蔗、柑橘等经济作物,管线经过桩号为NBZ237-NBZ248长约7.2km连片规模种植的香蕉林,其间夹杂有少量的木薯地和甘蔗地,管线穿过净香蕉林长度约为5km。
2. 香蕉林管道安装应引起重视的问题
在香蕉林中进行管道安装施工值得引起重视的问题是:
2.1 尽可能压缩施工作业带宽度,少占一寸土地,让蕉农们多收获一串香蕉。
2.2 保护并恢复好香蕉林的灌溉系统,维持香蕉的正常生长环境要求(见图1)。
图1 地上喷灌系统 2.3 在灌水的停息期内完成施工任务,保持香蕉林的灌溉周期节奏。
2.4 由于香蕉特殊的生长需要:当地蕉农采用一垅一垅的种植方式,种植前需对香蕉地进行深翻,采用二犁二耙的方式对香蕉林土地松动再施肥以满足香蕉种植需要,翻地深度一般为地表以下1米,故管道管顶覆土应在2.5m以上。
2.5 施工中,人员、机械、管道等尽可能不损坏香蕉树。 综合考虑各种因素,项目部特别制定了香蕉林管道安装施工方案。
3. 香蕉林管道安装施工方案要点
3.1 测量放线:对管道路由进行优化,尽量利用垅间路、边角、沟渠边空地,避开主水管线敷设管道,减少赔青费用,降低蕉农损失。
3.2 作业带清扫:正常作业带清扫按建设方规定的8m宽进行。我们在香蕉林按6m宽度进行清扫,尽量保证作业带横断面只砍除3株,局部特殊地段4株,不允许超4株香蕉树。
图2 管沟开挖3.3 拆除地面灌溉系统:先拆除软胶管,收集到作业带外香蕉林中,再手工切割PE主管线,拆除后放置在香蕉树垅间,不得损坏。
3.4 拆除地下水管线:在蕉农的配合下,人工开挖出地下水管线,按上面方法拆除,断口进行临时封堵,防止泥土、杂物进入堵塞水管线。
3.5 开挖管沟时,提前做好防坍方措施,必要时采用打钢管排桩以防塌方,然后按照要求进行管沟开挖(见图2)。
3.6 管线下沟、辅助工序完成后,及时进行回填,回填到地下供水管线标高。
3.7 地下供水管线恢复:按原位置对PE管热熔焊、连接。
3.8 继续地表土恢复。
3.9 地上供水管线恢复:对主水管线进行热熔焊、连接,恢复软胶管连接,完成施工任务。
4. 香蕉林管道安装施工管理措施
4.1 教育每一名员工,提高质量意识,增强农田和经济作物的保护意识。工农一家,既要圆满完成管道安装任务,又要使蕉农的损失降到最低。
4.2 对参加香蕉林管道安装施工机组的作业带占用宽度进行考核,少占的给予奖励,超占的扣罚。
4.3 提前购置准备好香蕉林水管线恢复材料、零部件及熔焊机等机具。 4.4 进行分段施工,服从香蕉林灌水周期节奏。 4.5 施工期间时值酷暑,香蕉林不透风,象蒸笼一样,蚊虫、毒蛇又多,要合理安排施工作业时间,防止中暑及蚊虫、毒蛇攻击,保证工人身体健康。 4.6 施工结束后听取蕉农意见,力求蕉农满意。 5. 结束语 经过项目部精心组织,在全体员工的共同努力之下,按期完成了香蕉林管道安装施工任务。经建设方、监理和质量监督部门检查,工程施工质量合格。通过压缩施工作业带宽度,少占用香蕉林地10000平方米(约15亩),按建设方要求,施工占地减少了25%,少砍伐约2000棵香蕉树。在项目部合理部署、科学安排下,加快施工节奏,在地貌恢复完成后,蕉农及时补植香蕉苗,降低了蕉农的损失。经过对沿线蕉农的回访,蕉农们对我单位在香蕉林地的管道安装所采取的少占香蕉林地、尽快恢复种植、降低蕉农损失的措施感到满意。