大朝山水电站工程建设的 DCS/C3标(大坝工程),由中国水电第八工程局和中国水电第三工程局组成八三联营体,联合中标承包。该标合同总金额4.04亿元,合同工期为1995年2月至2003年6月。DCS/C3标合同执行到2000年第二季度,共亏损10142.42万元,占中标总额的25.08%。经过5年多实践,成本亏损主要原因是:投资报价偏低,实际成本偏高,上缴工程局费用偏大。更主要的原因是联营体自身体制和管理存在问题和缺陷,诸如工地项目经理不稳定,内部承包不力、机电物资管理不到位、财务管理不善、技术管理有差距、管理机构多等问题。
Dashanshan Hydropower Station project construction DCS / C3 standard (dam project), by the China Hydropower Engineering Bureau and the Third Hydropower Engineering Bureau, the formation of eight three joint venture, the successful bidder contract. The total contract value of 404 million yuan, contract duration from February 1995 to June 2003. DCS / C3 contract implementation to the second quarter of 2000, a total loss of 101.4242 million yuan, accounting for 25.08% of the total bid. After more than five years of practice, the main reasons for the cost loss are: low investment quotations, high actual costs and large costs to the Engineering Bureau. The more important reason is the problems and flaws in the system and management of the joint venture, such as instability of the project manager in the construction site, ineffective internal contracting, inadequate management of mechanical and electrical materials, poor financial management, gaps in technical management and multiple management agencies.