今年三月以来,铁建所、四院、专业院在三处一队大力支持下,按计划开展了13号断层复合衬砌现场试验工作。试验段自DK2001+100~200,共100米。第1、2试验段各长35米由铁建所,四院共同承担,主要试验在Ⅲ类围岩中模注混凝土衬砌不同厚度的对比试验。第3试验段,段长30米,由专业院承担,在Ⅲ类围岩中采用低予应力锚杆代替普通砂浆锚杆和中间防水层改用喷涂乳化沥青。目前三个试验段初期支护的三个量
Since March this year, the Iron and Steel Institute, the Fourth Hospital and the Professional Institute have carried out field tests on the No. 13 composite lining as planned with the strong support of three teams. The test section from DK2001 +100 ~ 200, a total of 100 meters. The first and second test sections of 35 meters long by the Iron Works, the four homes shared, the main test in the Ⅲ type of rock in the concrete lining of different thickness contrast test. The third test section, paragraph 30 meters long, borne by the professional academy, in the Ⅲ type of rock in the low-stress anchor instead of ordinary mortar bolt and the middle waterproof layer instead of spraying emulsified asphalt. The three experimental sections are currently supporting three initial volumes