榆林炼油厂180万吨/年催化裂化装置工艺管道安装总量为39222米,其中碳钢管33796米,不锈钢管道1000米,合金钢管道4426米。该装置工艺管道系统工作介质多、试压系统大、管线跨区域多。在装置4月初开始工艺管道系统试压工作以来,用了不到一个月时间将试压工作顺利完成,给装置保质保量的按期中交夯实了坚定的基础。在整个催化装置工艺管道试压过程中,严格的按照工艺管道压力试验试压包机制进行,建立了一个有序、严密、高效的试压程序。
Yulin refinery 180 tons / year catalytic cracking unit process pipe installation total 39222 meters, of which 33,796 meters of carbon steel pipe, stainless steel pipe 1000 meters, 4426 meters of steel pipe. The device process pipeline system more media, pressure test system, pipelines and more cross-regional. Since the installation of pressure test for process piping started in early April, the pressure test has been successfully completed in less than a month, laying a solid foundation for the quality and quantity of the equipment on schedule. During the pressure test of the pipeline of the catalytic device, the process of pressure test of the process pipeline was strictly carried out, and an orderly, rigorous and efficient pressure test procedure was established.