由于各方面的原因,当年已完成坝址地形地质勘测、水位观测等一系列施工前期综合性勘测工作的布列依水电站工程被迫停工,直至10多年后才恢复施工。简述了俄罗斯21世纪第一座投运发电的布列依水电站的历史沿革、设计特点、地理位置和自然条件、水利枢纽布置及结构方案、以及水电站的工艺设备等。经过停工长达10多年后重新恢复工程施工的布列依水电站积累了丰富的施工经验,值得认真学习研究。
Due to various reasons, the Boulei hydropower project that had completed a series of pre-construction comprehensive survey work such as the geology survey and water level observation at the dam site was forced to stop work until 10 years later. The history, design features, geographical location and natural conditions of Russia’s first Bremen hydropower station put into operation in the 21st century are briefly described. The layout and structural schemes of hydro-junction and the process equipment of hydropower stations are also described. After a shutdown of more than 10 years to resume construction of the Boulei hydropower station has accumulated rich experience in construction, it is worth studying and studying conscientiously.