玛尔挡地处高海拔缺氧区,机械、人员效率明显偏低;工程区两岸岸坡陡峻,河谷狭窄,沿河公路布置困难,过坝交通洞、施工支洞与导流洞并行布置;导流洞工程具有进出口边坡高陡、洞室开挖断面大、体形复杂、工程量大等特点。导流洞工程于2012年3月31日正式开工,采取调整增设施工支洞、进口强行进洞、增设通风排烟、工期提前奖励和现场四方协商处理机制等措施,工程于2013年11月5日完工(剩余工程不影响截流),并于2013年11月28日实现过流,工程至今运行良好。其现场管理经验可供类拟工程项目借鉴和参考。
Mal is blocked in a high altitude and anoxic zone, and its mechanical and personnel efficiency is obviously low. The banks of the two sides of the project area are steep, the river valley is narrow, the layout of the highway along the river is difficult, the dam traffic tunnel, construction branch hole and diversion tunnel are arranged in parallel; Diversion tunnel project with import and export of high and steep slopes, tunnel excavation section, body complex, large quantities and so on. The diversion tunnel project officially started on March 31, 2012 and adopted measures such as adjusting and adding construction branch holes, importing forced-in holes, adding ventilation and exhaust smoke, early-warning of construction period, and on-site consultative handling mechanism. The project was completed on November 5, 2013 Day (the remaining works do not affect the closure of the river), and over-current was implemented on November 28, 2013. The project has operated well so far. Its on-site management experience can be used for reference and reference for similar projects.