西气东输二线项目规模庞大,面对众多的业务接口和信息接口,极易在设计质量、设计进度、配合施工、变更处理等方面出现问题。例如:下游用户分输量和分输口变化,设备资料不完备,运行单位在施工阶段对设计提出修改意见,地方规划导致路由确定困难,与地方协调能力欠缺,初设和地质勘察深度不够,专项评估和文件报批周期长等。同时,施工图设计漏项、地质勘探不详、设计不细,设计勘察分包缺乏有效的资质审查和管理,不及时执行集团公司的标准要求,设计联合体各单位之间缺乏有效的沟通与协调,设计单位工作效率低,图纸设计变更频繁等问题,均对施工进度和施工成本产生较大影响。基于对项目实施过程中设计管理问题的梳理和剖析,提出设计改进的可行性建议。
Due to the large scale of the Second West-East Gas Pipeline project, in the face of a large number of business interfaces and information interfaces, problems in design quality, design progress, cooperation with construction and alteration processing can easily arise. For example, the downstream users’ sub-transmission and sub-port changes, the equipment data are not complete, and the operation unit proposes modification opinions on the design during the construction phase. The local planning leads to the difficulty of routing, lack of coordination with the localities, Special assessment and approval of documents and other long cycle. At the same time, the construction drawings design omission, geological exploration is unknown, the design is not fine, the lack of effective investigation and management of design survey subcontractors, the group company’s standards are not implemented in time, the lack of effective communication and coordination between the various units of the design consortium , Low efficiency of design units, frequent changes in the design of drawings and other issues, have a greater impact on the construction progress and construction costs. Based on the combing and analysis of the design management problems in the project implementation process, the feasibility suggestion of design improvement is put forward.