混凝土搅拌站冬季施工时易受冷结冰,而传统的保温方法又无法保证正常的工作温度。为某HZS90型混凝土搅拌站设计加装自控温电加热保温系统,取得成效。自控温电加热保温系统采用内设加热电缆加热和外附保温层保温的方法,选择电加热元件防爆接线盒和电路空气短路开关,不影响原混凝土搅拌站的技术性能,系统运行安全有效,可保证施工工期,取得很好的经济效益。
Concrete mixing plant is vulnerable to cold icing during construction in winter, while the traditional insulation method can not guarantee the normal working temperature. For a HZS90-type concrete mixing plant design and installation of self-control temperature electric heating insulation system, and achieved results. The self-control electric heating system adopts the method of heating by the heating cable and insulation of the external insulation layer, and selects the explosion-proof junction box of the electric heating element and the air short circuit switch of the electric circuit, does not affect the technical performance of the original concrete mixing station, the system operation is safe and effective, Construction period can be guaranteed to achieve good economic returns.