大连国际客运站栈桥工程,是供乘客自码头到客运站上下船的架空廊道。其下有四条铁路和两条公路,为大连港装卸货的主要运输干线,因此建造栈桥必须断绝交通,影响运输任务。为了照顾运输,限定施工部门在48小时内完成施工任务。根据工程特点及时间要求,我们采取整体组装、整体拖运、整体吊装的方法,仅用36小时就全面完
The Dalian International Passenger Terminal trestle project is an overhead corridor for passengers to board and disembark from the pier to the passenger terminal. There are four railways and two highways underneath, which are the main transportation lines for cargo loading and unloading at Dalian Port. Therefore, construction of a trestle bridge must cut off traffic and affect the transportation tasks. In order to take care of transportation, the construction department is limited to complete the construction task within 48 hours. According to the engineering characteristics and time requirements, we adopt the method of overall assembly, overall haulage and overall lifting, which takes only 36 hours to fully finish