针对近年来黄河上游来水偏枯、龙羊峡水库处于低水位运行等特点 ,业主和设计单位对公伯峡水电站施工期的设计洪水流量进行了压缩调整。此举不但解决了截流时间推迟后大坝第一年的安全度汛问题 ,而且取得了可观的经济效益。这对其他工程建设也有一定的参考价值
In view of the characteristics of low water run of Longyangxia Reservoir in recent years, the owners and design units have compressed and adjusted the design flood discharge of Gongboxia Hydropower Station. This will not only solve the problem of flood control in the first year after the closure of the dam, but also achieve considerable economic benefits. This is also a certain reference value for other construction projects