正常停机在系统的日常停机以前,先用水把泵站管道和主管道中的矿浆排出。其步骤如下:打开主管道冲洗水泵上排放阀;起动冲洗水泵;停止矿浆增压泵并关闭增压泵排放阀;将冲洗水引入主管道泵站,清洗安全试验环路管道、泵站管道和主管道装置,最终引入主管道系统。在用冲洗水清除管道内矿浆的同时,用加压冲洗水冲洗贮罐歧管和增压泵
Normal Shutdown Prior to the daily shutdowns of the system, water is first used to drain the slurry from the pumping station and main pipe. The steps are as follows: open the main pipe flushing pump discharge valve; start flushing pump; stop the booster pump and turn off booster pump discharge valve; the flushing water into the main pipeline pumping station, cleaning safety test loop pipeline, pumping station pipeline and The main pipeline installation, the ultimate introduction of the main pipeline system. While flushing the slurry in the pipeline with flushing water, flush the tank manifold and booster pump with pressurized flush water