黄浦江两岸防汛墙加高加固工程,自1988年开始实施以来,已经历时近12年,当初计划化8.3亿元用7年时间完成208km,但是迄今为止已投资约13亿元,还剩近30km没有完成。在此期间,由于市区扩大又新增加了需要加高加固或改建的防汛墙107km,所以,市区防汛墙现在总共为315km。本来计划将市区防汛墙全面进行加高加固或重建后,可使防汛墙的设防能力达到千年一遇标准,然而由于水情工情发生变化,高潮位累累突破历史记录,黄浦公园站的
Since its implementation in 1988, it has been nearly 12 years since the implementation of the Flood Control Wall Enhancement Project on both banks of the Huangpu River. Since the planned 830 million yuan has been completed for 208 km in seven years, an investment of about 1.3 billion yuan has been invested so far, nearly 30 km left not done. During this period, the urban flood control wall now totals 315km due to the expansion of the urban area and the addition of 107km of flood control walls which require further reinforcement or alteration. Originally planned to increase or reinforce the urban flood wall in a comprehensive manner, the fortification capability of the flood wall could reach the standard of one thousand years. However, due to the changes in water conditions and the high tide overrun history, the Huangpu Park Station